Question 57
The table below is a schedule management table for a given project. The diagram on the right shows the tasks and standard number of days for each task. In order to reduce the time length for completing this project by three days, what is the minimum required additional cost in tens of thousands of yen?
a) 9
b) 11
c) 14
d) 15